Foundations of one of the most heavily loaded railways in the world
For the foundations of one of the most heavily loaded railways in the world (2,000 tons of the space rocket), Menard developed an alternate solution combining dynamic replacement and vertical drains as an alternative to excavation and replacement of the mangrove, a difficult task, given Guyana’s weather conditions. A 300 t full-scale load test was carried out confirming the results of 3D finite element calculations. The final measurements showed less than 2.5 cm of settlement.